Who performs Independent Cost Estimates (ICE) for major DoD acquisitions?

Prepare for your Certified Defense Financial Manager (CDFM) Exam 1. Study with comprehensive flashcards and multiple-choice questions. Understand core defense financial management concepts and boost your exam readiness today!

Multiple Choice

Who performs Independent Cost Estimates (ICE) for major DoD acquisitions?

Explanation:
Independent cost estimates for major DoD acquisitions come from an objective government cost-analysis function—the Office of the Secretary of Defense Cost Analysis and Improvement Group (CAIG). The ICE is produced independently of the program office and the contractor, providing an unbiased, authoritative estimate of program costs that supports decision-making, budgeting, and program oversight. The program office may prepare its own cost estimate, but that is not considered the ICE; contractor incremental estimates are not ICE either. In practice, the ICE is performed by OSD CAIG or an equivalent Cost Analysis Improvement Group, which is why this option best fits how major DoD acquisitions are evaluated.

Independent cost estimates for major DoD acquisitions come from an objective government cost-analysis function—the Office of the Secretary of Defense Cost Analysis and Improvement Group (CAIG). The ICE is produced independently of the program office and the contractor, providing an unbiased, authoritative estimate of program costs that supports decision-making, budgeting, and program oversight. The program office may prepare its own cost estimate, but that is not considered the ICE; contractor incremental estimates are not ICE either. In practice, the ICE is performed by OSD CAIG or an equivalent Cost Analysis Improvement Group, which is why this option best fits how major DoD acquisitions are evaluated.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy